How Long Does a Home Renovation Take? (Dallas, TX)

Free Estimate on SiteCalls Answered by a Live Person, 24/7Background-Checked TechniciansA Local Team in Dallas
A new bay window with a cushioned seat
A new wood side gate with black hardware
A new concrete driveway with a paver border
A stone counter, tile backsplash and open shelf after a kitchen remodel
A remodeled hall bathroom with subway tile and a floating vanity
A garage converted into a guest room and home office
New architectural shingles with a clean valley
A new casement window over a kitchen sink
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate
Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

How Long Does a Home Renovation Take in Dallas, TX?

Most Dallas renovations run longer than the schedule you were quoted, and the reason is usually not labor or cabinets. It’s what the walls hide. A kitchen remodel quoted at six to ten weeks can stretch toward fourteen when demolition exposes a diagonal drywall crack and a sill plate that has been quietly rotting since the last hard freeze. For a full home addition, expect 14-22 weeks in Dallas; for a ground-up ADU, 16-24 weeks. Any honest timeline here has to include a discovery window, because Dallas’s blackland clay rarely lets a project open up clean.

Rowan Construction Group Dallas puts every one of those numbers in writing before anyone picks up a tool, along with the one figure most contractors leave off the sheet: the time it takes to resolve what demo turns up.

An open kitchen and dining area after a remodel

The Discovery Window: Why Dallas Timelines Slip

Here’s the pattern. A kitchen remodel is scheduled for eight weeks. Demo happens on day three, and behind the drywall is a diagonal crack running from a corner of the window trim. In East Dallas and Oak Cliff, where a large share of the housing stock is 1950s pier-and-beam brick ranch, that crack is usually a blackland-clay foundation telling you the piers have settled. Under the floor, the sill plate may be rotted, and the subfloor may be out of level enough that cabinets won’t sit square. None of that gets priced on demo day unless the contractor knew to look for it up front.

So we build the window into the schedule: one to two weeks for assessment before framing starts. During that window we lift the floor, photograph the piers and the sill, and write down what we found, not what we felt about it. If the fix is foundation-leveling piers, you get a scope and a flat price. If it’s just dried-out framing, you get a shorter schedule back. What you don’t get is a silent four-week gap where nobody can tell you where the job stands.

Our technicians have up to 19 years of experience reading exactly this kind of condition in Dallas homes, and they’ll tell you which findings are common and which are unusual. Sticking doors in September after a dry Texas summer are classic heave, and the fix is almost always piers under the slab, not patching the drywall.

Baseline Timelines by Trade, in Weeks

Generic renovation articles tell you a kitchen “takes a few months.” That isn’t useful when you’re planning around a move-out date or a rental. These are the baselines we commit to in Dallas, before the discovery window is added to the schedule:

  • Kitchen remodel: 6-10 weeks (a small kitchen runs toward the low end; $9,000-$20,000 for a small kitchen, $14,000-$45,000 for a full one)
  • Bathroom remodel: 3-5 weeks ($5,000-$12,000 small, $9,000-$28,000 full)
  • Full home addition: 14-22 weeks ($45,000-$130,000)
  • ADU, ground-up: 16-24 weeks ($90,000-$220,000)
  • Garage conversion: 10-16 weeks ($30,000-$80,000)

The range inside each line reflects scope and finish, not contractor speed. A walk-in shower with a properly sloped shower pan and a Schluter waterproofing membrane will cost more time than a tub-to-shower conversion with a pre-formed base, and it should, because the tile assembly has to be right the first time.

Permit-to-Punch-List: Which Phase Moves Most in Dallas

Break the schedule into phases and only one of them is genuinely unpredictable here: City of Dallas Development Services review. For residential additions, plan review currently runs 3-6 weeks, and that figure swings with staffing and plan-set completeness. The rest of the timeline is controllable:

  • Design and material selection: 2-3 weeks
  • Permit review: 3-6 weeks (the variable one)
  • Demolition and discovery: 1-2 weeks
  • Rough-in and framing: 2-4 weeks
  • Finishes and punch list: 2-3 weeks

A complete plan set is the single best lever on the review phase. Revisions caused by missing plumbing or electrical detail cost you weeks you can’t get back.

A freestanding soaking tub in a remodeled primary bathroom

The Other Silent Timeline Killer: Material Lead Times

You can have a perfect schedule and still lose six weeks because the cabinetry was ordered late. KraftMaid and Wellborn cabinets typically run 3-5 weeks from order; Cambria countertop fabrication runs 2-3 weeks after templating, and templating can’t happen until the base cabinets are set. Sequence it wrong and the countertop order waits behind the cabinet install, which waits behind the electrical rough-in, which waits behind the permit. The difference between an eight-week and a fourteen-week kitchen is often the date the cabinet order went in, not the day the crew showed up.

That’s why we release material orders the moment the signed scope is in hand and the permit is submitted, not the day demo starts. Fixtures like a Toto or American Standard toilet, a Kohler faucet, or tile from a stocking supplier carry shorter lead times, but anything made to order has to be locked early.

How Signed Change Orders Compress the Surprise

Every renovation has a surprise. What differs is how long the surprise costs you. Under Clause 1 of The Haven Standard, the price is written before anyone starts, and no work proceeds on a change until the change-order is signed. In practice, that means a scope change discovered during the discovery window gets a written price and a schedule impact, and you sign or you don’t, in days rather than weeks of unanswered phone calls and disputed invoices.

This discipline is the reason Rowan’s projects finish within a few percent of the number the customer agreed to, across more than 4,000 jobs delivered since 2007. It also protects the timeline, because an unsigned change stalls the job while an unsigned phone promise stalls the relationship.

How Much Does a Dallas Renovation Cost?

Cost and duration move together, so here’s the pricing that pairs with the timelines above. Every figure is a flat written price with a written scope, not an estimate that grows later:

Project Typical Price Range Typical Timeline
Small bathroom remodel $5,000-$12,000 3-4 weeks
Full bathroom remodel $9,000-$28,000 4-5 weeks
Small kitchen remodel $9,000-$20,000 6-8 weeks
Full kitchen remodel $14,000-$45,000 8-10 weeks
Home addition $45,000-$130,000 14-22 weeks
ADU construction $90,000-$220,000 16-24 weeks

If you’re looking at a larger scope across the house, our home page lays out all seven trades we cover and how they sequence together. For anyone who already has a written estimate from another contractor, Rowan offers a free second opinion on it, line by line, at no charge. Bring it in and we’ll tell you what’s missing.

Common Local Scenarios and What They Add

Three situations we see most often in Dallas, and what each adds to the schedule:

  • Pier-and-beam ranch in East Dallas with Foundation Sill Rot: add 1-2 weeks for shimming and sill-plate repair before framing.
  • Dense infill townhome near Knox/Henderson: tight lot access adds days to material staging and can trigger a crane rental for a heavy delivery.
  • 1950s one-story on shallow slab in Oak Cliff: a slab crack found mid-demo can mean engineered piers, which can add 2-3 weeks and a second permit review.

Contractors in this city have to move fluently between a 1950s one-story and a modern two-story infill on the same block, and those two structures don’t fail the same way. That’s the local knowledge a written timeline has to reflect.

FAQs

Getting started with Rowan in Dallas

Every project starts with a conversation and a written price. Here is how to take the first step.

A project lead walking the house with the homeowner during a free estimate

Free on-site estimate

A project lead walks the job with you, measures it and hands you a written, line-item price. No obligation.

Book an estimate
A crew arriving at a home with materials and tools

Your Dallas team

A local vetted partner works across Dallas and the towns around it, to the same written standard as every Rowan job.

Areas we serve
A worker laying floor protection before work starts

Read our written promise

What we promise on every job, written down, with the terms spelled out before any work starts.

Our promise
Need Construction help in Dallas? Licensed & insured · free written estimates
Call (833) 954-5327
Local Service Coverage

Request a Free Estimate in Dallas

Tell us what you need - Rowan Construction Group Dallas responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Prefer to text? Text Now
Call Now - 24/7 Dispatch